Cost of customs upgrade project set for 40% hike

Tk 1,700cr project spends only 1% of budget in 3 years
Rejaul Karim Byron
Rejaul Karim Byron

Three years after launch and with 99 percent of its budget unspent, a nearly Tk 1,700 crore customs modernisation project is set to be presented to the Executive Committee of the National Economic Council (Ecnec) today with a proposal to extend its deadline and raise costs by nearly 40 percent.

The Customs Modernisation and Infrastructure Development project was launched in April 2023 with World Bank (WB) financing to modernise key customs offices, including Chattogram, Benapole and Dhaka.

It was scheduled for completion by March 2026. As of June 2025, only Tk 5.14 crore had been spent of the original Tk 1,686 crore budget, of which Tk 1,475 crore was a WB loan.

Although Tk 113 crore has been allocated in the current fiscal year, the government is now seeking to extend the project’s duration and increase its cost.

A senior planning ministry official said a revised proposal has been listed for presentation at today’s scheduled Ecnec meeting.

The proposal, seen by The Daily Star, recommends increasing the project cost by 39 percent to Tk 2,344 crore, with the WB loan increasing by 34 percent, or Tk 507 crore. It also proposes extending the deadline to June 30, 2028.

The proposal attributes the cost increase to revisions made at the detailed design stage, after the initial estimate was based on conceptual design.

The earlier exchange rate assumption of Tk 102 per US dollar has been revised to Tk 122. Rising construction rates and higher VAT and tax rates have also contributed to the escalation.

At present, Dhaka Customs handles large volumes of air freight and courier consignments, Chattogram Customs manages 90 percent of the country’s import-export activity, and Benapole Customs oversees the bulk of land trade.

The project will introduce modern infrastructure and technology at these offices to speed up import-export operations, reduce tax evasion, and strengthen the detection of money laundering.

Planned works include construction of office buildings, laboratories, warehouses and residential facilities at Chattogram Customs House, as well as a new building for the Customs, Excise and VAT Training Academy. Baseline, midline and endline time-release studies will be conducted at major customs stations.

A tariff policy implementation plan will also be prepared, the existing tariff structure reviewed, and the feasibility of tariff reforms assessed using ASYCUDA World, National Single Window and Automated Risk Management System software.